灵寿县圣邦矿产品加工厂
![](https://img.zhaosw.com/upload/images/202103/25/cdb050a8-16c2-41af-89b4-1a6a4442b27d_source.jpg)
![](https://img.zhaosw.com/upload/images/202103/17/4aefd811-f33e-4cee-87b0-9dac2a4d95ef_source.jpg)
![](https://img.zhaosw.com/upload/images/202103/17/57dc045d-b9ea-45b9-a3a8-3c9126e43fe9_source.jpg)
![](https://img.zhaosw.com/upload/images/202103/17/85e13b51-5940-47ae-8e72-1f5ee9276b93_source.jpg)
![](https://img.zhaosw.com/upload/images/202103/16/4ad8f47f-e39f-4939-91ec-74629ff32271_source.jpg)
![](https://img.zhaosw.com/upload/images/202103/16/3a8448c0-6558-42a4-bfe6-547e03329676_source.jpg)
![](https://img.zhaosw.com/upload/images/202103/16/800e8f94-7120-4635-a363-43c33608bd35_source.jpg)
![](https://img.zhaosw.com/upload/images/202103/16/1105894e-2d62-4921-8fb2-6ab0a1aebafc_source.jpg)
![](https://img.zhaosw.com/upload/images/202103/16/7e3cd14f-3bc7-4968-833d-ac9cc05dbc2a_source.jpg)
![](https://img.zhaosw.com/upload/images/202103/22/d64a929d-7347-4363-a066-71327c1f166b_source.jpg)
![](https://img.zhaosw.com/upload/images/202103/19/3d7092eb-6640-4227-8c58-88d614545137_source.jpg)
![](https://img.zhaosw.com/upload/images/202103/19/2869e836-b90f-4015-8a08-d3ee08fee8fa_source.jpg)
灵寿县圣邦矿产品加工厂
金刚砂耐磨地面材料由耐磨损骨料同优//质水泥,添加剂等组成,预拌生产,配比严格控制、质量稳定,在工地直接应用。金刚砂地面材料利用干洒式施工,与混凝土基层整体固化后,在地面上形成一层密实坚硬,高 度耐磨损,防尘的面层。
用途 适用于大部分工业厂房,仓库,停车场,货仓式超//市等,尤其是有车辆行走的区域。
施工工艺流程
混凝土浇筑并整平→抹光机振实、刮平→次 铺撒金刚砂地坪材料→抹光机揉压、抹平→二次撒金刚砂地坪材料→抹光机揉压、抹平→边角压光→整体抹平压光→养护。
耐磨硬化地坪施工工艺: 1、混凝土基层要求:新浇注的混凝土地面强度要求大于C25,平整度落差要控制在3mm以内;
2、清洁混凝土地面:对于新施工的混凝土地面要使用磨光机抹平压实,地面的平整性,养护15天左右,确保混凝土地面已固化干实后再进行打磨处理,清//除表面的灰尘等;对于旧的混凝土地面或其他硬化地面,应清//除表面的杂物,脱落的结构等,然后清扫地面;
3、干燥地面的处理:对过于干燥的旧地面,使用清洁水充分润湿混凝土表面;
4、硬化剂的使用:硬化剂即混凝土密封固化剂,可以采用涂刷或喷洒的方式,充分润湿预处理的混凝土表面,并保持湿润1-2小时;期间如果局部硬化剂干燥过快应及时加补硬化剂保持湿润。为了使硬化剂能充分的渗//透到混凝土内部,可以使用毛刷或滚筒等工具不断地摩擦地面;
5、当气温较高时,表面的硬化剂由于水份蒸发的原因很快变粘稠,可喷涂少量水稀释变稠的硬化剂,但用量不宜过多。
6、硬化地面抛光:施工后的地面可以用机械器具进行人工抛光,增加地面的光泽度和平整度;
7、耐磨地坪的养护:硬化地坪施工完成后应养护7天左右方可投入使用,期间可以使用耐磨地面养护剂或水进行养护。